New Kusile unit powers up, 8 months ahead of schedule

Apr 16 2019 13:49
Lameez Omarjee

For the first time on Sunday Kusile Unit 3 produced power, according to an internal memo to Eskom staff.

According to the note from Eskom's chief operating officer Jan Oberholzer, sent out to staff on Monday, the synchronisation of the unit happened eight months ahead of the scheduled December 2019. This is the third out of six Kusile units which have been synchronised to the national grid.

"The first synchronisation of Unit 3 marks a key milestone towards the full commercial operation of the unit.

"The next step will be the testing and optimisation of the unit which will result in it generating full power of 800MW of electricity, to be fed into the national grid for the country's consumption," Oberholzer said.

The unit is expected to be commercially operational, six months after the first synchronisation - or November 2019.

The first Kusile unit went live in August 2017. Each of the six units will produce 800MW of electricity, Fin24 previously reported.

At a previous briefing earlier in April on the status of the electricity system, Eskom board chair person Jabu Mabuza said that the construction of Kusile and Medupi Power stations would not be halted. The construction of both plants costs R36bn (R18bn each).

Mabuza explained that the benefit of concluding construction would outweigh the cost of stopping the projects.

Construction started as far back as 2007.

According to a report from the Sunday Times, the Special Investigating Unit is probing an alleged theft of R139bn from Eskom related to the construction of Medupi and Kusile power stations.


eskom  |  jan oberholzer  |  jabu mabuza  |  power  |  load shedding  |  medupi  |  kusile
NEXT ON FIN24X

 
 
 
 

Company Snapshot

Money Clinic

Money Clinic
Do you have a question about your finances? We'll get an expert opinion.
Click here...

Voting Booth

What do you think about private healthcare in SA?

Previous results · Suggest a vote

Loading...