Share

Eskom under fire as Ingula costs said to balloon to R36bn

Cape Town – Eskom’s board is facing calls to appear before Parliament with documents relating to the Ingula pumped storage scheme, which has allegedly seen costs spiral from R8.9bn to R36bn.

On July 27, President Jacob Zuma unveiled the first of four turbines at Ingula, which is on the border of KwaZulu-Natal and the Free State. A report broadcast on Carte Blanche on Sunday claims that Zuma's appearance was a rushed pre-elections media stunt.

The pumped-storage hydroelectric plant uses water from an upper dam, which is released and passes through four 333 MW turbines before ending up in the lower dam during peak hours. The water is then pumped back up to the top to dam in low-peak hours.

However, the turbines are massively over budget and delayed, with all four turbines having originally meant to go live in 2013. The earliest they will now all be commercially operational is in 2017.

Carte Blanche interviewed an insider and a mining expert who worked at Ingula, who said the underground contractor was paid billions more than they should have in bonuses, advances and flimsy compensation events, even as the contractors skimped on safety.

The contractor - CMI Joint Venture – comprises of two Italian companies, which allegedly have a track record of over-runs and corruption. The third company is PG Mavundla Engineers, which is owned by Philani Mavundla, a friend of Zuma that offered to pay for Nkandla, according to Carte Blanche.


President Jacob Zuma and Public Enterprises Minister Lynne Brown at the launch of Ingula on 27 July 2016. (Photo: GCIS)

Eskom board must address Parliament - DA

Democratic Alliance (DA) MP Natasha Mazzone told Fin24 on Monday that she will write to the chairperson of the Portfolio Committee for Public Enterprises to ask for Eskom’s board to be summoned to the committee.

“Eskom must explain what the situation is at Ingula,” she said. “We will call on Eskom to make their procurement policy and all tender policies public with regard to Ingula.

“We are told these documents are sensitive,” she said. “But these are public funds and they belong to the citizens. We can’t be commercially sensitive if it is already in the public domain.”

If the request fails, Mazzone will send a Promotion of Access to Information Act request to Eskom, with stringent deadlines to meet.

Mazzone said the alleged mismanagement of Eskom’ new build programme – which includes Medupi, Kusile and Ingula - is the reason why she has asked Public Enterprises Minister Lynne Brown on several occasions to release stakeholder contracts and to ensure all procurement and tender policies are made public. “Every time she agrees to do so, but she never does,” said Mazzone, citing Medupi's alleged irregular tender with Hitachi.

Outa calls for independent inquiry

The Organisation Undoing Tax Abuse (Outa), which has its own whistle-blower input with regards to Ingula, said on Monday that it is time the government institutes a full independent inquiry into the financial management and auditing controls throughout Eskom.

“We find the regular repetition of excessive runaway costs of large capital expenditure projects at Eskom, a gross violation of the Public Finance Management Act and fiduciary duties of the Management and Board at Eskom,” said Ivan Herselman, Outa’s director of legal affairs.

“Any serious over-expenditure of this nature needs to be thoroughly and independently investigated and accounted for, to the public.”

Last week, Eskom’s recent electricity tariff increase was ruled as having transgressed correct procedures and it now has to revise the tariff increase and face a possible class action for this dire situation.

“The over expenditure issue at Ingula has once again provided the public with more reason to be incensed at the high electricity tariff hikes over the past nine years,” said Outa chairperson Wayne Duvenage.

“Eskom’s track record on capital expenditure projects at Medupi, Kusile and others, can be described as nothing short of diabolical and the Ingula matter just adds more fuel to Eskom’s fire of incompetence and unacceptably high operating and capital costs. One can imagine what lies ahead if Eskom are left to manage a Nuclear Energy build project.”

President Jacob Zuma and Public Enterprises Minister Lynne Brown at the launch of Ingula on 27 July 2016. (Photo: GCIS)

Eskom defends its contractor

Eskom spokesperson Khulu Phasiwe told Fin24 on Monday that all units at Ingula will be in commercial operation within the second half of 2017.

“All payments made to contractors were done in accordance with the approved contract and in line with Eskom’s procurement policies and procedures,” he said.

“The history of these contractors was considered, via Business Intelligence Reports, before contracts were awarded.

“Unit 3 repairs are underway, with the unit still on track for commercial operation as planned. Discussions with the insurer are ongoing, and the final costs have not been determined yet.”

Phasiwe said in their programme last night, Carte Blanche "started off by casting aspersions on Eskom’s assertion that Ingula was producing over 900MW on 27 July 2016 – the day of Unit 4’s official launch.

“Carte Blanche said this was impossible as that unit only generates 333MW. In a desperate effort to show ‘Eskom’s lies’, Carte Blanche forgot to note that Ingula’s two other units, namely Unit 1 and Unit 2, were - and still are - being synchronised and were producing 333MW each to the grid, even though they have not come into commercial operation yet.”

Phasiwe lambasted the programme for not allowing Eskom time to give its side of the story, with the MNet investigative programme highlighting that Eskom had missed its deadlines to respond and offered them an interview on Monday. However, Phasiwe told Fin24 that there is "no point" to have the interview now.

Contractor compensated for accident, despite allegations it was to blame

An insider told Carte Blanche that the South African people have been let down by Eskom in an epic way. “The money for the project was borrowed money and must be paid back,” he said. “It will take years to recover from this level of incompetence and waste.”

Six people died and seven people were injured in 2013 when a platform in the incline high-pressure shaft failed.

Eskom and the contractor blamed the foreman who died in the accident, but a report into the incident has not been released to the public, Carte Blanche explained. It said CMI Joint Venture claimed about R1bn in compensation for an accident that some experts claim was their fault.

Mike Hall, a mining expert who was the underground project manager at Ingula from 2009 to 2012, told Carte Blanche that he was “appalled that the contractor was not adhering to the mine’s health and safety” regulations.

Peter Bailey, chairperson of health and safety at the National Union of Mineworkers, told Carte Blanche: “In our preliminary investigation that we’ve done, we found that negligence was the order of the day there. 

“If Eskom has paid this amount of money, this thing now goes much broader than just a labour relations issue,” he said. “No wonder we have had these massive spikes in electricity prices.

“Society has got to make a noise. They don’t care about their expenditure,” he said, calling for the replacement of Eskom’s executive and board.

An insider told Carte Blanche: “The sums involved in the CMI claims were out of proportion to the delays or the cost of the delays. If the contractor submitted to a forensic audit, my belief is that the profits enjoyed by CMI would be obscenely large. There was someone in upper Eskom management who was instructing the site team to certify massive payments to CMI.”

CMI said it did not want to provide comment on the Carte Blanche story.  

GRAPHIC: How Ingula works


Update: Joy Summers, Carte Blanche investigative producer, sent Fin24 the below right of reply on Tuesday in response to Phasiwe's statements regarding the interview:

Carte Blanche has a string of e mails to prove the following:

We started asking Eskom for an interview in late May - we have an e mail record of it. We also asked in June – at a point we were going to do the interview with Mr Koko and Mr Masango on the same day, but Eskom’s logistics didn’t allow for that and we also decided that perhaps we should just concentrate on Optimum and then focus later on Ingula.

However, after the interview that Devi Sankaree Govender conducted with Mr Koko, Eskom decided that they would henceforth only do live interviews with Carte Blanche. I suppose its uncomfortable being caught out on national television as Mr Koko was, regarding the prepayment to a Gupta linked company, but instead of taking it on the chin, Eskom implied by their refusal to entertain our Ingula request, that somehow we cut the programme to make it appear as if Mr Koko was not telling the truth. We had to cut the interview down but I can assure you that Mr Koko would not have been saved the embarrassment of his “mistake” had we put the whole interview on Carte Blanche.

Back to Ingula. So we hit an impasse with Eskom – they would only do live interviews and Carte Blanche felt that we could not accommodate a live interview as this is not our format. Instead we suggested that we do the interview and place the entire interview on our website,  as well as cut the insert for Sunday night as we have been doing for the last 25 years.

Eskom said they would consider that and we waited. And waited. We asked again and gave Eskom a final deadline of Wednesday evening last week at 5 pm. The deadline came and went and we sent Eskom the attached mail on Thursday morning last week, in a final attempt to get comment. Still no reply.

Eventually, Friday lunchtime, they responded and said they would grant us an interview on Monday.  We agreed to do the interview. It would be perfectly legitimate for Eskom to respond this week as they had indicated. Since the story went out the only response we have is that they were generating 990 MW as Mr Masango said. Please see below for Eskom’s own press release about this in June.

I doubt they can dispute any of the figures as they are all documented, and it is my view, a far more likely reason for their cancellation on Monday morning is that they didn’t want to face Carte Blanche’s Ms Devi Sankaree Govender in an interview, as she would have had all the documented facts at her disposal. We stand by our story.

Eskom statement on June 13: Ingula unit 3 is currently under repair based on an incident that was experienced during the optimization process, post synchronisation.  This unit was synchronised to the National Grid on 6 March 2016 and supported the Grid until 6 April 2016 when the incident occurred.  Ingula unit 2 was synchronized to the National Grid on 22 May 2016 and is under optimisation.  Ingula unit 1 is still under construction.  Ingula units 3, 2 and 1 are on track for commercial operation in 2017.

Read Fin24's top stories trending on Twitter:


We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.29
-0.7%
Rand - Pound
23.87
-1.1%
Rand - Euro
20.58
-1.2%
Rand - Aus dollar
12.38
-1.1%
Rand - Yen
0.12
-1.2%
Platinum
943.50
+0.0%
Palladium
1,034.50
-0.1%
Gold
2,391.84
+0.0%
Silver
28.68
+0.0%
Brent Crude
87.29
+0.2%
Top 40
67,314
+0.2%
All Share
73,364
+0.1%
Resource 10
63,285
-0.0%
Industrial 25
98,701
+0.3%
Financial 15
15,499
+0.1%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders