Cape toll project flawed - City

Cape Town - Sanral's public notice on the Winelands tolling project was unlawful because the national roads agency never took a proper board decision committing to the project, the Western Cape High Court heard on Friday.

Geoff Budlender, for the City of Cape Town, argued that the SA National Roads Agency Limited (Sanral) had been "ducking and diving" to conceal the absence of such a decision, as it rendered their case invalid.

He was presenting argument for an urgent interdict preventing Sanral from going ahead with the N1/N2 Winelands Toll Highway Project until a court reviewed the legality of the project.

The city wants a court order forcing Sanral to provide certain documents it had requested on the decision-making process, to assist it in the review which is pending in the same court.

Judge Ashley Binns-Ward stated that the court and the city did not know what evidence Sanral would lead in the review. Budlender said this was precisely the case because Sanral did not want it to be known.

"There was no board decision," Budlender said, adding that therefore Sanral had no right to publish a notice in the Government Gazette in 2008.

"Sanral entered into a concessionaire contract, which is unlawful."

The city argued the decision-making process on the toll project was flawed. It believed there was evidence to suggest the environmental minister at the time authorised the project based only on its environmental impact, not the socio-economic impact on the surrounding communities.

The toll project has been in the pipeline for nearly a decade. A record of decision was first issued in 2005, then re-issued by then minister of tourism and environmental affairs Marthinus van Schalkwyk in February 2008.

Chris Loxton SC, for Sanral, argued that the city was approaching the matter in an "upside down" manner. He said the socio-economic impact could only be considered once Sanral had authority to upgrade the roads, because only then could it determine how to fund the work.

The steps to be followed in this regard were to start concluding a concessionaire contract, calculate the total costs involved, and then see if it was feasible to collect the funding required through tolls alone or through co-contributions.

At present, Loxton said on Friday, the costs were unknown.

In court documents, Loxton said the decisions into which the city was demanding insight were not part of the current court proceedings. Furthermore, he said, the city had failed to explain why the documents would be relevant.

He suggested the city was abusing the court process to obtain a document on which it could build an argument to block the toll road, because it did not support the user-pays principle on roads.

"The city appears to hold the view that it is entitled to conduct an inquiry spanning many years, to establish whether or not there is some document that will assist it in obstructing the implementation of the user-pays principle.

"It is submitted that it may not use a judicial review process to do so."

Sanral criticised the city for taking three years to institute legal proceedings.

The proposed concession route along the N1 extends from west of the R300 interchange through to Sandhills. The N2 portion of the proposed toll road concession extends from west of the R300 to Bot River.

According to a diagram on Sanral's website, 106km of the N1 and 70km of the N2 would be tolled should the project go ahead.

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.02
+1.0%
Rand - Pound
23.79
+0.7%
Rand - Euro
20.40
+0.8%
Rand - Aus dollar
12.40
+0.7%
Rand - Yen
0.12
+1.2%
Platinum
925.50
+1.5%
Palladium
989.00
-1.6%
Gold
2,332.33
+0.7%
Silver
27.40
+0.9%
Brent Crude
88.02
-0.5%
Top 40
68,437
-0.2%
All Share
74,329
-0.3%
Resource 10
62,119
+2.7%
Industrial 25
102,531
-1.5%
Financial 15
15,802
-0.2%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders