Total goes ahead with Angolan oil project

Paris - France's Total said it had decided to go ahead with the Kaombo oil project offshore Angola after reducing its cost by $4bn to $16bn, an advance that could help Angola keep up oil output over the long run.

The decision to invest in the ultra-deep sea project, which has been repeatedly delayed because of its cost, is seen as important for Africa's No 2 oil producer to replace older fields and hit its production targets.

In recent years, a number of other large-scale projects around the world have fallen victim as oil companies have reduced global investment and returned cash to shareholders.

"Total has significantly optimized the project's design and contracting strategy in recent months. Kaombo illustrates both the group's capital discipline and objective to reduce capex," Yves-Louis Darricarrere, Total's president for upstream, said in a statement on Monday.

Half of the cuts came from a reassessment of the project's specifications, using a "'just good enough' approach rather than 'the best possible'," Arnaud Breuillac, the company's exploration and production chief told Platts on Friday.

The company decided, for example, to build its two 115 000 barrels per day (bpd) floating production storage and offloading units by making alterations to two very large crude carriers (VLCCs) instead of building them from scratch, he said.

These units will have a shorter lifespan than purpose-built ones, which could last up to 35 years, but using the converted VLCCs and other less bespoke equipment could save $2bn.

It is saving another $1bn by agreeing with the government to cut the number of work hours done on the project locally, because the rates are more expensive in Angola than elsewhere.

The project in Block 32 is scheduled to start up in 2017 when it will have a production capacity of 230 000 bpd, the French oil company said.

"Globally, deep water costs are rising - this year by almost 20%, so the fact that Total could find slack in its capex to continue with its Angola project shows how investors view Angola's longer-term offshore prospects," said Rolake Akinkugbe, head of energy and natural resources coverage at FBN Capital.

"By and large, they are bullish."

In a similar move last year, Britain's BP scrapped bespoke plans to develop its Mad Dog 2 project in the Gulf of Mexico, opting instead for a repeatable model it had used before. BP said it thought the old model could recover 90% as much oil at a fraction of the cost.

Total is already the top operator in Angola, with equity production of 186 000 bpd, mainly due to its Girassol, Dalia and Pazflor deepwater fields in the huge Block 17. The blocks it operates produce a total of 600 000 bpd, over a third of the country's output.

Total also confirmed on Monday that it was on track to start output at the Clov project in Block 17, which will have a production capacity of 160 000 bpd in mid-2014.

Replacing older fields

"With the investments it is making in Blocks 17 and 32, it will be very difficult for any other oil company to overtake Total as the leading operator in Angola," said Jose de Oliveira, head of the Energy Nucleus at Luanda's Catholic University. Angola wants to increase production to 2 million bpd next year from 1.73 million bpd in 2013 and then maintain that level for five years.

Still, analysts say the country's plans to ramp up production have proven more challenging than expected due to technical problems and declines at older fields.

Credit rating agency Fitch on Thursday revised Angola's outlook to stable from positive, citing challenges to the oil sector as one of the main drivers behind the decision.

"Kaombo is very important if Angola wants to put production at 2 million bpd, because output at some of the older fields, namely in blocks 14 and 15, is declining," Oliveira said.

Total and Angolan state-owned firm Sonangol each hold 30% stakes in Block 32, while Angolan-Chinese joint venture Sonangol Sinopec International has 20%, Exxon Mobil's Esso unit 15% and Portugal's Galp 5%.

The Kaombo project is located about 260 km off Luanda in water depths of 1 400 to 1 900 metres.

Total shares were up slightly at €47.835 at 12:00.


We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.06
+0.8%
Rand - Pound
23.75
+0.8%
Rand - Euro
20.37
+0.9%
Rand - Aus dollar
12.38
+0.9%
Rand - Yen
0.12
+1.0%
Platinum
907.10
-0.6%
Palladium
987.00
-1.8%
Gold
2,327.23
+0.5%
Silver
27.37
+0.8%
Brent-ruolie
88.02
-0.5%
Top 40
68,289
-0.4%
All Share
74,252
-0.4%
Resource 10
61,497
+1.7%
Industrial 25
102,616
-1.3%
Financial 15
15,836
-0.0%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders