Court gives Eskom power to act on Medupi

Johannesburg - Eskom is inching closer to bringing its recalcitrant contractors at the Medupi power plant to book.

This week it scored a Supreme Court of Appeal victory, which strengthens its ability to bring Hitachi Power Africa to account for the fiasco at the Medupi site.

Five judges confirmed that the utility is entitled to ask for guarantees that the Mizhuo Corporate Bank of Japan gave to ensure Hitachi does its work properly.

Hitachi is one of the contractors responsible for delays in getting Medupi online. It is now not expected to generate power until next year, missing this year’s deadline.

According to an Eskom spokesperson, the utility will not necessarily continue with the claim of R600m it made in February against the guarantee.

Eskom and Hitachi, which is 25% owned by the ANC’s investment arm, Chancellor House, and which was controversially awarded a R20bn tender on the Medupi project, have been locked in battle since November 2012 over welds in the power plant’s boiler that do not meet the required standard.

Eskom threatened to make a claim under a performance bond, but Hitachi was granted an interdict preventing Eskom from making demands against the Japanese bank. This was put aside this week by the appeal court.

Eskom was able to call in guarantees relating to another contractor, Alstom, raising concerns that Hitachi was not acting within its contract, possibly owing to its ANC links.

Eskom said it had negotiated with Hitachi since the initial court order and is about to sign an agreement. Thursday’s ruling is expected to strengthen Eskom’s bargaining position significantly.

While considerable progress has apparently been made to repair the faulty work, Eskom now has a very strong contractual position because it still has to continue working with Hitachi for some time until Medupi is built.

Eskom’s other main contractor, Alstom, is also on very thin ice.

Eskom said in a presentation to the National Council of Provinces select committee on labour and public enterprises that it would call in another contractor if Alstom did not fix problems at Medupi.

Alstom’s control instrumentation system is the “brain” of the power plant.

Eskom has already called in a performance guarantee from Alstom.

Eskom apparently started to assign preparatory work to Siemens in July for another solution for Unit 5 and Unit 6. These units will be the first to be put into operation.

Eskom said this week that Alstom had deadlines and, if these weren’t met, it would decide whether to proceed with the contract or cancel.

Any cancellation could cause further delays to a project that is already way behind schedule and running way over initial budget estimates.

- City Press

 
We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.08
+0.4%
Rand - Pound
23.63
+0.8%
Rand - Euro
20.34
+0.3%
Rand - Aus dollar
12.26
+0.3%
Rand - Yen
0.12
+0.4%
Platinum
943.50
-0.7%
Palladium
1,025.00
-0.4%
Gold
2,399.61
+0.9%
Silver
28.74
+1.8%
Brent Crude
87.11
-0.2%
Top 40
67,314
+0.2%
All Share
73,364
+0.1%
Resource 10
63,285
-0.0%
Industrial 25
98,701
+0.3%
Financial 15
15,499
+0.1%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders