Cape Town – Eskom’s delay in signing power purchase agreements with renewable energy independent power producers (IPPs) whose bids were approved by the Department of Energy could result in manufacturers going out of business, National Treasury warned in its 2017 Budget Review.

“Lack of clarity on Eskom’s plans to connect new IPPs to the electricity grid … has prompted concerns that some renewable energy equipment manufacturers could go out of business,” it said.

Eskom has said it will sign contracts with the IPPs, but the industry has warned that the power utility is being unreasonable with escalating costs to connect them to the national grid and wants some bidders to lower their own costs of supplying power to Eskom.

This followed President Jacob Zuma’s instruction to Eskom in his State of the Nation Address in February, in which he said Eskom will connect the latest bidders to the grid.

“The 2017 State of the Nation speech addressed an important aspect of this policy uncertainty, noting that Eskom will sign outstanding power-purchase agreements for renewable energy in line with procured rounds,” Treasury said.

In his Budget speech at Parliament on Wednesday, Finance Minister Pravin Gordhan pointed out that the continuation of the IPP programme was “imperative” to boost investment in the short term.

In its Budget Review, Treasury said the IPP programme “boosted power generation, attracted R194.1bn in private investment and created thousands of jobs”.

“Transforming the energy sector, with growing opportunities to generate electricity from renewable sources, can open the market to new, innovative businesses and boost employment creation.”

“IPPs have helped to reduce South Africa’s carbon emissions and fostered the development of new renewable energy firms, some of which have become exporters.”

The IPP programme was also imperative in Zuma’s bid to transform the economy to address poverty, inequality and unemployment.

“On average, black South Africans hold 31% of shares across the IPP supply chain,” Treasury said. “Local communities own 11% of the projects and are expected to receive R29.2bn in income over 20 years. Contracts under negotiation have the potential to generate over R500bn in investment and create more jobs.”

“Government plans to continue the IPP programme and extend the successful model to other sectors,” it said.

Value added in the electricity sector fell by 2.9% in the first three quarters of 2016 as electricity-intensive sectors such as mining contracted.

This was due to the “increased power supply from Eskom and IPPs, Eskom’s enhanced maintenance programme and low demand stabilised supply,” Treasury said.  

Regarding the Department of Energy’s Integrated Energy Plan and the Integrated Resource Plan, Treasury said these proposals will be open to public comment until the end of March 2017.

“Fiscal sustainability and consumer affordability will inform government’s choices on the preferred generation mix,” it said.  

In line with the national commitment to transition to a low-carbon economy, IPPs will generate 14 725 MW from renewable energy sources.

“Since August 2011, six procurement bid windows have been completed under the Renewable Energy Independent Power Producer Procurement Programme.

“The programme has procured combined generation capacity of 6 376 MW since its inception. Of the renewable energy capacity procured, 4 001 MW is at various stages of development.

“More than 11 000 gigawatt-hours have been added to the national grid since 2011.

“Private-sector investment in the programme amounts to R201.76bn to date, of which R49.1bn is from foreign investors and financiers.”

* Visit our Budget Special for all the budget news and in-depth analysis.

Read Fin24's top stories trending on Twitter:
We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.19
-0.1%
Rand - Pound
23.86
-0.1%
Rand - Euro
20.42
-0.1%
Rand - Aus dollar
12.29
+0.1%
Rand - Yen
0.12
-0.3%
Platinum
953.70
+0.4%
Palladium
1,031.00
+0.2%
Gold
2,384.26
+0.2%
Silver
28.38
+0.5%
Brent Crude
87.11
-0.2%
Top 40
67,190
0.0%
All Share
73,271
0.0%
Resource 10
63,297
0.0%
Industrial 25
98,419
0.0%
Financial 15
15,480
0.0%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders