Eskom has cunning plan to avoid future load shedding

Cape Town – Instead of decommissioning some of Eskom’s aging coal power plants, the power utility wants to keep some of them in “extended cold reserve” that can be rejuvenated in 10 years should there be any emergency short falls due to new build delays for example.

Acting executive for generation Willy Majola told Fin24 on Friday that it doesn’t make sense to permanently close some of the aging coal stations, whose units could be extended, especially in a time of crisis.

“If we send bulldozers to Hendrina Power Station instead of putting it into extended cold reserve, we might find ourselves in trouble later on,” he said.

Eskom has been temporarily switching off 13 units from eight power stations in times of power surplus, with the idea that some might be switched off for a longer period of time.

This all depends on the Department of Energy’s draft energy plan that will determine what mix of new energy build will be developed in the foreseeable future. This could be a mix of nuclear, gas, renewables and coal. It is expected to be finalised next year February.

If, for example, government decides to build a nuclear power station by 2025, then Majola believes some of the coal power stations not required due to an excess capacity of power could be put on ice and switched on if there was ever a delay in the new build programme.

“In the integrated resource plan, Eskom said excess capacity will peak at 6 500 MW in 2020 and then this will drop to 500 MW in 2025,” he said. “If you have decommissioned these stations (close down permanently), and you are late on new build, you are going to get into trouble.

“If you decommission the stations today, but demand grows and new build is late, then we will go into load shedding. Therefore, we cannot talk about decommissioning the coal stations. We should not decommission stations to ensure we don’t fall into load shedding.”

Majola said Eskom is experiencing “operational excess capacity, which is seasonal”.

As such, he said Eskom has put 13 units totalling 3 700 MW on “cold reserve”: four at Komati, two each at Kriel and Grootvlei, and one each at Camden, Majuba, Arnot, Hendrina and Tutuka. “The call up time ranges from 16 hours to five days,” he said.

Netwerk24 reported on Thursday that Grootvlei and Komati have already been placed in extended cold reserves, which means that it has been scaled down to such an extent that five days are needed before the units can be restarted.

Majola said energy regulator Nersa recently published dispatch rules, which gives Eskom the criteria of which units must be operational, based on a least-cost model. This also takes into consideration the security of the system, the technical capabilities of the units, as well as the transmission stability, he explained.

The aim, interim Eskom CEO Johnny Ddladla said recently, was for the utility to manage the surplus power generation in order to save costs.

“Things can change from day-to-day,” Majola said. “It depends on the criteria set by Nersa. We expect that as we commission more units at Medupi and Kusile, the excess is going to grow.”

“Our projections are that excess will decrease as the load grows. Then, as the excess decreases, you will need more units operational.”

Majola said that during this period of excess capacity, Eskom needs to put some units or the entire plant into extended cold reserve. Eskom previously stated that it will temporarily close the Hendrina, Grootvlei and Komati power stations over the next three to four years, to trim its surplus power and manage power generation costs optimally.

However, Majola said this five-year production plan was based on short run marginal costs. “In this case, those power stations would not be needed and this is largely influenced by coal.”

“However, if you put units in extended cold reserves you have to take into account total cost, which includes a present value analysis, as well as capex and opex costs,”  he said. “We are busy with that study. That will tell us whether it should be units or power stations that are put into extended cold reserves.”

“We know we have to put stations in extended cold reserve because the excess is there,” he said. “We need to justify which coal stations go into reserve. Cold reserve is a risk mitigation with regard to system adequacy.”

“Eskom believes the excess will decrease and we will need new load. The integrated resource plan will tell us when to expect new power and from where.”

SUBSCRIBE FOR FREE UPDATE: Get Fin24's top morning business news and opinions in your inbox.

Read Fin24's top stories trending on Twitter:

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
18.88
+0.3%
Rand - Pound
23.85
+0.2%
Rand - Euro
20.39
+0.2%
Rand - Aus dollar
12.32
+0.2%
Rand - Yen
0.12
+0.2%
Platinum
908.05
0.0%
Palladium
1,014.94
0.0%
Gold
2,232.75
-0.0%
Silver
24.95
-0.1%
Brent Crude
87.00
+1.8%
Top 40
68,346
0.0%
All Share
74,536
0.0%
Resource 10
57,251
0.0%
Industrial 25
103,936
0.0%
Financial 15
16,502
0.0%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders