Share

Why SA’s public finance watchdog failed its mandate on nuclear

The Parliamentary Budget Office had 10 months to prepare its findings about the cost of a nuclear programme, but its final report was little more than a summary of other institutions' work, explains Seán Mfundza Muller, senior lecturer in economics at the University of Johannesburg.

South Africa’s Parliamentary Budget Office is a largely unknown but important institution. It was established in 2009 to provide technically credible, independent advice to members of parliament about public finance and economic issues.

Evidence from other countries suggests that the credibility and independence of such an office is only truly tested when it is asked to provide advice about a politically significant issue. South Africa’s Parliamentary Budget Office recently faced just such a test when it advised MPs on the country’s proposed procurement of nuclear energy. The nuclear plan has been estimated to cost as much as R1 trillion.

But an analysis shows that the office’s recent presentation and report to MPs was sorely lacking. It failed to produce a credible analysis of the likely total cost of the proposed nuclear programme or its impact on public finances.

Although the office, contrary to international best practice, does not make its presentations and reports public, it is possible to access them on the Parliamentary Monitoring Group’s website.

Financial implications for future generations

In 2015 the office was asked by the then chair of the Standing Committee on Appropriations in Parliament, Paul Mashatile, to advise on the proposed nuclear procurement. He made it clear that the office’s primary focus had to be public finances: "Where are we going to get this money, the R1 trillion? We are dealing with questions of affordability…when all is said and done…and [not burdening] our children and grandchildren."

Mashatile’s position is compatible with the law. Appropriations committees are supposed to focus on public expenditure.

The Parliamentary Budget Office had 10 months to prepare its findings. Yet its final report was essentially a desktop summary of various other institutions' work. It compared the cost of producing a given unit of energy across different energy generating sources.

This itself is complex terrain. Some experts argue that nuclear is the cheapest of the low emission options. But that conclusion has been challenged. Either way, a public finance-oriented institution like the Parliamentary Budget Office is not well-placed to adjudicate on such issues.

Worse still, the office’s presentation and report were phrased in a way that allowed both proponents and opponents of nuclear to interpret the analysis as supporting their preferred conclusion. This has led some observers to incorrectly report that the office’s findings opposed the nuclear programme.

Besides vague statements about factors related to public finances, the office’s report contained no substantive analysis of electricity demand. It also did not have a total cost of the project or its affordability. MPs were left uninformed about the possible implications for public finances.

Credible, independent analysis needed

In other countries, analysis by parliamentary budget offices fulfils two functions. It informs MPs and provides citizens with a genuinely independent, trustworthy perspective on complex and contested public finance issues.

There’s a wide range of voices arguing different positions on nuclear in South Africa. Power utility Eskom, various nuclear power-related institutions and politicians in one faction of the governing ANC are arguing that nuclear is needed and affordable. On the other side, civil society organisations, opposition parties, renewable energy producers and independent energy experts argue vociferously that nuclear is undesirable, unnecessary and unfeasible.

The average, impartial citizen may be unsure who to believe. Meanwhile, statements by South Africa’s president, deputy president and the ministers of energy and finance have made it clear that "(nuclear procurement will only be pursued at) a scale and pace the country can afford".

So the obvious question is: who will give ordinary South Africans a credible affordability analysis? A report by a competent, genuinely independent and non-partisan institution could have carried significant weight.

The Parliamentary Budget Office repeatedly asserted that affordability issues were not in the “mandate” from parliament’s Standing Committee on Appropriations. This is difficult to verify because the office does not publish research requests, final terms of reference or its reports and presentations. But it seems unlikely that the financial feasibility of nuclear was omitted from the terms of reference given the motivation articulated by Mashatile.

So what should the office have done?

What should have been done

First, it should have attempted as detailed a bottom-up costing of the nuclear programme as possible in the time available. This would include:

  • the likely costs of building power plants,
  • the associated costs of financing that investment,
  • nuclear waste disposal costs,
  • future decommissioning costs, and
  • insurance costs or liabilities that arise from adequately accounting for the risk of a nuclear disaster.

There are many international peer institutions the office could have called on. These include, for instance, the US’s Congressional Budget Office.

Nor did the office need to reinvent the wheel locally. The Department of Energy has produced a nuclear project costing and the National Treasury has also drafted one. Although the energy department’s costing is classified, all staff working with parliament recently underwent a state security agency clearance process. This means that, with the support of the relevant committees, the office’s staff could have obtained a copy.

Second, the estimated cost should have been used to assess the likely impact on public finances. It barely requires an analysis to show that, whether it costs R500 billion or R1.5 trillion, funding the proposed nuclear programme directly is unaffordable. Having briefly noted that, a public finance analysis would shift to considering the various public-private partnership and “vendor financing” models likely to be used instead.

These instruments have their uses. The problem is that they shift the risks and expenses to future years. That is when either consumers, government or both would have to start repaying the successful bidder. This potentially allows politicians to take bad decisions now and be long gone by the time the negative consequences become apparent. So an important aspect of the analysis would be assessing the financial implications for future time periods and future generations.

In doing this analysis, it is critical to account for what would happen if the power produced by nuclear plants is not needed for the foreseeable future - which I have argued current evidence suggests. The office should have requested energy demand forecasts from Eskom and the energy department.

These failures further denied South Africans and their elected representatives the opportunity to make a sound, well-informed judgement about the programme. It also raises the question of whether there is any purpose in having independent fiscal institutions if they demur when dealing with politically sensitive topics.The Conversation

This article was originally published on The Conversation. Read the original article.

Read Fin24's top stories trending on Twitter:

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.05
-0.7%
Rand - Pound
23.98
-0.3%
Rand - Euro
20.55
-0.4%
Rand - Aus dollar
12.36
-0.1%
Rand - Yen
0.13
-0.7%
Platinum
894.10
-0.3%
Palladium
996.00
-0.6%
Gold
2,193.32
-0.1%
Silver
24.41
-1.0%
Brent Crude
86.09
-0.2%
Top 40
67,889
+0.3%
All Share
74,074
+0.2%
Resource 10
56,132
+0.9%
Industrial 25
103,554
+0.3%
Financial 15
16,492
-0.2%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders