Costly delays upset reactor renaissance, keep nuclear at bay

Tokyo - Costly delays, growing complexity and new safety requirements in the wake of the triple meltdown at Fukushima are conspiring to thwart a new age of nuclear reactor construction.

So-called generation III+ reactors were supposed to have simpler designs and safety features to avoid the kind of disaster seen in Japan almost six years ago. With their development, the industry heralded the dawn of a new era of cheaper, easier-to-build atomic plants.

Instead, the new reactors are running afoul of tighter regulations and unfamiliar designs, delaying completions and raising questions on whether the breakthroughs are too complex and expensive to be realised without state aid. The developments have left the industry’s pioneers, including Areva and Westinghouse, struggling to complete long-delayed projects while construction elsewhere gains pace.

“The cost overrun situation is driven by a near-perfect storm of societal risk aversion to nuclear causing ultra-restrictive regulatory requirements, construction complexity, and lack of nuclear construction experience by the industry,” said Lake Barrett, a former official at the US Nuclear Regulatory Commission.

Toshiba, Japan’s biggest maker of nuclear power plants, is the latest to join a list of companies facing impairments in the pursuit of cutting-edge reactors.

Tokyo-based Toshiba said in December it may have to write down billions on an acquisition by its Westinghouse unit due in part to cost overruns at two nuclear plants it’s building in the US. The company aims to announce the details of the impairments on February 14, which Bank of America Merrill Lynch expects to be 551 billion yen ($4.9bn), while SMBC Nikko Securities Inc. forecasts 500 billion yen.

“We are reviewing the future of our nuclear power business outside Japan, but nothing has been decided at this time, including future development,” spokeswoman Yuu Takase said by e-mail in response to questions about the size of the writedown.

The March 2011 Fukushima meltdown that shuttered Japan’s industry sent ripples around the world, forcing companies and regulators to seek safer designs. The US shale boom, meanwhile, slashed prices for gas, coal and oil and undercut rising costs to develop nuclear energy.

Ballooning costs

In 2015, the investment cost to develop a new nuclear plant was $5 828 per kilowatt, up from $2 065 in 1998, according to a World Nuclear Association report. In Europe, construction of a new nuclear facility in France seen costing $7 202 per kilowatt, compared with $2 280.

Toshiba isn’t alone. France’s Areva is seeking a €4.5bn bailout from the French government after running into delays and escalating costs at its next-generation EPR reactor at Olkiluoto in Finland, which is almost a decade late. It’s also selling its nuclear reactor construction business to Electricite de France. An Areva spokesperson declined to comment on Wednesday.

Two EPRs at Hinkley Point in southwest England to be built by EDF are expected to run £18bn. The cost of an EPR being built by the company at Flamanville in France has tripled since construction started in 2007. The project is six years behind schedule. A spokesperson on Wednesday said the issues can be attributed to an industry, which has lost skills due to a building lull, struggling with a cutting-edge design.

Toshiba, one of Japan’s three biggest reactor suppliers, first made a bet on the future of atomic power in 2006, when it purchased a controlling stake in Westinghouse for $5.4bn.

As recently as March, nuclear power business was seen as a growth driver, accounting for almost a fifth of net sales by fiscal year 2018, according to a company presentation at the time. The business comprised 13% of net sales in the latest fiscal year.

Westinghouse boasted that its generation III+ AP1000 reactor was the safest on the market, employing a simpler, modular design that could be rolled out in record time. In 2015, Westinghouse took over construction of two nuclear projects in Georgia and South Carolina when it bought contractor CB&I’s nuclear business for $229m. The purchase also resulted in a settlement between Westinghouse, CB&I and the utilities that owned the plants over delays and cost overruns.

US overruns

Following the purchase, Westinghouse was sued by CB&I over a $2bn accounting dispute related to cost overruns at four reactors in the US. While the case was dismissed, CB&I is appealing the decision and moved forward on a process with an independent auditor to decide who bears the charge.

The projects, split over two sites and overseen by utilities Southern and Scana, incorporate the AP1000. Cost overruns have ballooned, with Southern’s share at about $1.3bn and Scana’s at least $831m.

“I don’t know of any recent examples of new, large, complex technological construction projects that have come in on time and on budget,” Allison Macfarlane, a former chairperson of the US Nuclear Regulatory Commission, said by e-mail.

The industry has no agreed-upon definition for generation III+. Broadly, the reactors are expected to withstand an airplane strike and the cooling systems should operate for at least three days without electricity.

‘Get up to speed’

While the industry works through the challenges of the technology in Europe and the US, competitors in Asia are moving forward. South Korea started its first APR-1400 last year, and the UAE picked the design for its first batch of reactors. China says its homegrown Hualong One, which it’s building at home and aims to sell overseas, uses third-generation nuclear technology.

Hualong One is part of China’s state-backed nuclear program that plans to boost capacity more than 70% by 2020. The world’s second-biggest economy will almost triple capacity to nearly 100 gigawatts by 2026, making it the biggest market globally, according to BMI Research.

And in Hungary, Russia has agreed to finance 80% of an estimated $12bn to build two Rosatom VVER-1200 reactors. Russia is ready to raise that to 100% by “tweaking” the deal, President Vladimir Putin said at a joint briefing with Hungarian Prime Minister Viktor Orban on Thursday.

One fundamental problem facing developers is the slowed pace of construction since a nuclear building boom in the 1970s and 1980s, according to Mark Hibbs, a senior fellow at the Carnegie Endowment for International Peace’s Nuclear Policy Programme.

“You get better at building reactors when you can keep at it,” Hibbs said by e-mail. “At some point Areva and Westinghouse may get to the point of doing that with generation three, but they would have to get up to speed first.”

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.07
+0.5%
Rand - Pound
23.60
+1.0%
Rand - Euro
20.32
+0.3%
Rand - Aus dollar
12.24
+0.5%
Rand - Yen
0.12
+0.4%
Platinum
943.20
-0.8%
Palladium
1,035.50
+0.6%
Gold
2,388.72
+0.4%
Silver
28.63
+1.4%
Brent-ruolie
87.11
-0.2%
Top 40
67,314
+0.2%
All Share
73,364
+0.1%
Resource 10
63,285
-0.0%
Industrial 25
98,701
+0.3%
Financial 15
15,499
+0.1%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders