Johannesburg - Eskom has signed two electricity
purchase contracts with independent power producers (IPPs) and will soon
conclude another four.
These are the first agreements Eskom has entered
into with private electricity providers, which will add 300MW of generation
capacity to South Africa's electricity network by July. Another 100MW will be
added by March.
After the electricity crisis in January 2008
government decided to introduce private electricity generation, but the
struggle to establish a legal framework has so far held up the
process.
The six contracts for the purchase of private
electricity are being entered into in terms of a decision by the National
Energy Regulator (Nersa) in February, when the medium-term tariff increases
were announced.
Nersa determined that Eskom could spend R2.3bn on
buying electricity from private producers this year, R4.3bn next year and
R5.8bn in 2012.
This is a special measure to increase Eskom's
generating capacity until a full regulatory framework for independent power
producers can be established. The framework will eventually include an
independent buyer and seller of electricity.
On Sunday the electricity giant's spokesperson Andrew
Etzinger said that these six contracts formed part of the Medium-Term
Power Purchase Programme (MTPPP), one of two categories of private power
producers from which Eskom is permitted to buy electricity.
It could involve co-generation by large industrial
consumers that sell electricity as a byproduct to Eskom, or fully-fledged
producers which generate power from purchased sources of energy. Etzinger
declined to say how the contractors' power would be generated.
Hopes for more power by July
Scaw Metals, an Anglo American subsidiary, recently
published a tender for the construction of an electricity plant that, as an
independent, would deliver electricity to Eskom.
Department of energy director general Nelisiwe
Magubane said the two contracts concluded so far had been sent to Nersa for
approval, after which the IPPs could proceed with their developments.
As soon as approval has been given, she said, the
parties will start environmental impact studies as well as other
pre-development work. Once this has been concluded, the providers
should be able to supply electricity to South Africa within a few
months.
The 400MW is being permitted in terms of government's
integrated resource plan 1 (IRP1), which was announced in December last
year. The IRP1 also provides for 1 025MW of electricity being bought from
renewable energy sources by 2013.
The department of energy is still working on the IRP2.
Certain amendments will be made to the IRP1 and these are expected to be finalised
later this year. One possible amendment is that the IRP2 could set higher
targets for IPPs, as well as for renewable energy.
It costs Eskom about 31c per kilowatt hour (kWh) to
generate electricity. The utility has previously indicated that it
expects to pay independent power producers 65c per kWh for the
electricity they
generate.
Eskom chief executive for
planning Kannan Lakmeeharan said two contracts have already been drawn up for some of the four
IPPs Eskom is still negotiating with. These just need to be signed.
As far as the last two of the six are concerned, a few
issues need to be sorted out before their contracts can be signed. These terms
are being negotiated.
Lakmeeharan said Eskom hopes to have access to about
300MW of the power that the IPPs can deliver by July 2010.
It hopes that the remaining 100MW will be ready by
March 2011. These dates are of course dependent on approval from the IPPs as
well as Nersa.
Lakmeeharan said Eskom estimates a further 1 000MW to 3 000MW of power
could be obtained from IPPs.
- Sake24.com
For business news in Afrikaans, go to
www.sake24.com.