Name and shame Medupi culprit - DA

Cape Town - A sub-contractor connected to Hitachi Power Africa is believed to be behind the delay in completing the first phase of the Medupi power station, the DA said on Friday.

It said this emerged from a two-day oversight visit to the Limpopo project by parliament's public enterprises portfolio committee.

"MPs on the visit were informed that a Hitachi Power Africa sub-contractor was responsible for the faulty welding on the boilers," Democratic Alliance MP Natasha Michael said.

Michael said officials from Hitachi had told MPs the sub-contractor had misled both Eskom and Hitachi into believing that quality control tests on the boilers had been conducted.

"This was not done. As a result, all the welds on the boiler in unit six had to be re-checked and many replaced," she said.

The name of the subcontractor was not disclosed during the visit.

Name and shame

"South Africans deserve to know which entity is responsible for faulty service delivery and misleading both Eskom and the country as a whole," Michael said.

The DA, however, welcomed the fact that criminal charges were laid against the company.

The party would ask Public Enterprises Minister Malusi Gigaba to confirm the name of the sub-contractor in a parliamentary question.

Other reasons cited for the delays were the failure of French company Alstom to ensure software for the plant's operating system was working, and labour unrest.

"Alstom is responsible for the control and instrumentation system at the plant. Many of the other contractors have now completed their work and await this system to become operational."

Lingering strikes

On the continuing wildcat strikes, Michael said: "The committee met with organised labour and was informed that despite various mechanisms and agreements put in place, the implementation and communication between Eskom, contractors, and organised labour remain problematic."

Michael would ask that Gigaba be summoned to appear before parliament's public enterprises committee to receive a report from MPs, and address them on their concerns.

Earlier this month, Eskom said in a statement the new power station would probably begin contributing to the national grid only in the second half of next year. The previous target was December.

The Medupi power station is a new dry-cooled, coal-fired power station being built by Eskom near Lephalale in Limpopo.


We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.21
-0.3%
Rand - Pound
23.90
-0.3%
Rand - Euro
20.46
-0.4%
Rand - Aus dollar
12.33
-0.2%
Rand - Yen
0.12
-0.3%
Platinum
943.60
-0.7%
Palladium
1,012.00
-1.7%
Gold
2,380.03
+0.0%
Silver
28.27
+0.2%
Brent Crude
87.11
-0.2%
Top 40
66,783
-0.6%
All Share
72,832
-0.6%
Resource 10
62,993
-0.5%
Industrial 25
97,637
-0.8%
Financial 15
15,425
-0.4%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders