Name and shame Medupi culprit - DA

Jul 26 2013 15:36 Sapa

Public Enterprises Minister Malusi Gigaba inspects the Medupi power plant earlier this year. (Sapa)

Related Articles

MPs to interrogate Medupi officials

Eskom fighting to impose penalties

Numsa seeks Medupi probe

No heads will roll at Eskom, says Gigaba

Ramphele: Medupi to hit poor the hardest

Fraud scandal rocks Medupi

 

Cape Town - A sub-contractor connected to Hitachi Power Africa is believed to be behind the delay in completing the first phase of the Medupi power station, the DA said on Friday.

It said this emerged from a two-day oversight visit to the Limpopo project by parliament's public enterprises portfolio committee.

"MPs on the visit were informed that a Hitachi Power Africa sub-contractor was responsible for the faulty welding on the boilers," Democratic Alliance MP Natasha Michael said.

Michael said officials from Hitachi had told MPs the sub-contractor had misled both Eskom and Hitachi into believing that quality control tests on the boilers had been conducted.

"This was not done. As a result, all the welds on the boiler in unit six had to be re-checked and many replaced," she said.

The name of the subcontractor was not disclosed during the visit.

Name and shame

"South Africans deserve to know which entity is responsible for faulty service delivery and misleading both Eskom and the country as a whole," Michael said.

The DA, however, welcomed the fact that criminal charges were laid against the company.

The party would ask Public Enterprises Minister Malusi Gigaba to confirm the name of the sub-contractor in a parliamentary question.

Other reasons cited for the delays were the failure of French company Alstom to ensure software for the plant's operating system was working, and labour unrest.

"Alstom is responsible for the control and instrumentation system at the plant. Many of the other contractors have now completed their work and await this system to become operational."

Lingering strikes

On the continuing wildcat strikes, Michael said: "The committee met with organised labour and was informed that despite various mechanisms and agreements put in place, the implementation and communication between Eskom, contractors, and organised labour remain problematic."

Michael would ask that Gigaba be summoned to appear before parliament's public enterprises committee to receive a report from MPs, and address them on their concerns.

Earlier this month, Eskom said in a statement the new power station would probably begin contributing to the national grid only in the second half of next year. The previous target was December.

The Medupi power station is a new dry-cooled, coal-fired power station being built by Eskom near Lephalale in Limpopo.


Follow Fin24 on Twitter, Facebook, Google+ and Pinterest.

alstom  |  da  |  hitachi  |  eskom  |  medupi  |  natasha michael  |  malusi gigaba
NEXT ON FIN24X

 
 
 

Read Fin24’s Comments Policy

24.com publishes all comments posted on articles provided that they adhere to our Comments Policy. Should you wish to report a comment for editorial review, please do so by clicking the 'Report Comment' button to the right of each comment.

Comment on this story
22 comments
Add your comment
Comment 0 characters remaining
 

Company Snapshot

We're Talking About: Small Business

Standard Bank is looking for 12 entrepreneurs to participate in a 10-part TV series. They could win a R1m investment into their dream.
 
 

ANCYL: Not voting would be blasphemy

Not voting in the forthcoming elections would be blasphemy, the ANCYL says in a statement commemorating the 50th anniversary of struggle icon Nelson Mandela's Rivonia trial speech.

 
 

Latest elections multimedia

Why Jack Parow wants you to vote on 7 May
The ad the SABC doesn't want to air
Elections 2014 in one cartoon
This year's election posters

Money Clinic

Money Clinic
Do you have a question about your finances? We'll get an expert opinion.
Click here...
Loading...